  1. Question 1.1 · Activity planning and critical path · 1 mark

    Identify what planned activities contain: option A, end dates; option B, resource allocation; option C, start date; option D, all of the above; option E, none of the above.Show the full question
  2. Question 1.2 · Activity planning and critical path · 1 mark

    Determine what the first step in software project planning is: option A, determine the budget of the project; option B, select an organisational model for team work; option C, determine the project constraints; option D, establish the objectives and scope of the project; option E, none of the above.Show the full question
  3. Question 1.3 · The project manager and process · 1 mark

    Identify the basis of successful project management: option A, identifying the project stake holder's objectives; option B, ensuring that these objectives are met; option C, accurate information; option D, all of the above; option E, none of the above.Show the full question
  4. Question 1.4 · Evaluation and investment appraisal · 1 mark

    Select how net profit is calculated: option A, adding total cash inflows to the initial investment; option B, adding total expenses to the initial investment; option C, deducting total cash inflows from total cash outflows; option D, deducting total expenses from total income; option E, deducting total expenses from the initial investment.Show the full question
  5. Question 1.5 · Evaluation and investment appraisal · 1 mark

    Identify what needs to be taken into consideration when calculating the payback period: option A, the initial investment; option B, whether cash inflows are received at the end or the beginning of the period; option C, the interest rate; option D, A and B; option E, A and C.Show the full question